Chapter 23
A New Terminal
The longest and incidentally the last piece of railroad construction
fostered by President Whitcomb is represented in the line between Owen
and Duluth, built 1905-1909. The Owen-Duluth extension, 161 miles in length,
projects from Owen (on the Chicago-St. Paul main) northwest on the longest
stretch of straight track in the state, skirting the Chequamegon National
Forest on the way to the Lac Court Oreilles Indian Reservation. Here the
right-of-way cuts the southwest corner of the reservation and swings in
a wide detour around the Court Oreilles Lake Region to resume the northwesterly
course to Superior-Duluth.
When built, the line ranged through the one remaining section of Wisconsin
which might be termed wilderness, about 4,000 square miles in area still
untouched by any north and south railroad. The best timber had been slashed
before 1900, but enough cutting remained to support active lumber operations.
The territory north and northwest of Owen had long been a mecca for bolder
sportsmen who took their deer hunting and bait casting seriously.
In the areas adjacent to the Flambeau, Jump, and Mondeaux Rivers, trackless
marsh land and windfalls occurred, spotted with dense growths of pine and
hemlock. Most of this area is now included in the Chequamegon National
Forest.
In the 80's and 90’s, nationally known leather and tannery interests
built permanent log camps here and employed large crews of woodsmen "tree-skinners"
in the work of stripping the bark from live hemlock trees, the bark to
be used in tanning processes. Solid trains of hemlock bark in four foot
lengths, corded high and wired on flat cars were no uncommon sight on the
Ashland and St. Paul divisions of the Central as late as the middle 90's.
Much of this area remained to be settled and developed when work on
the Owen-Duluth extension commenced in 1905.
Exclusively a Wisconsin Central project, the extension was legally established
within two corporations; namely, the Owen & Northern Railway Company,
incorporated May 24, 1904; and the Lake Superior & Southeastern Railroad
Company, incorporated October 8, 1904. The former received a charter to
construct the line from Owen to Ladysmith, 45.64 miles; the latter chartered
to continue the project from Ladysmith to Superior, l08 miles.
The Owen & Northern had done some clearing and grading of the roadbed
through the agencies of independent contractors not affiliates with the
Central and was engaged in construction work when sold to the Central June
11, 1905. The Central assumed the contracts end completed the 45.52 miles
between Owen and Ladysmith in July. This section of the extension was opened
to traffic August 6, 1906. At Ladysmith direct connections and freight
transfer facilities were established with the Soo Line east and west Main
line.
In 1906 contracts were awarded by the Central to H. F. Balch, Rice Lake,
Wisconsin, and the Lantry Construction Company of Kansas City, to construct
the railroad from Ladysmith to the Superior-Duluth area. The Balch contract
covered construction from Ladysmith to Superior, 103 miles; the Lantry
Construction Company contracted to execute the work on the Duluth terminal
and southward to Superior, 7 miles.
The Lake Superior & Southeastern experienced difficulties and had
made little progress before it was purchased by the Wisconsin Central Railway
Company June 11, 1906.
From here in, the Central handled its own construction work, Superior
to Ladysmith, under the direction of Chief Engineer C. N. Kalk, who succeeded
Robert Tweedy.
The right-of-way from Ladysmith to Superior leads through some of the
most extensive lowlands and "blue-berry marshes" in the state, all of which
required filling or build-up pile trestle work. For two and one-half years
steam shovels threw dirt; work trains hauled vast quantities of ballast
and filling material for embankments across the marshlands. Five large
steel bridges and forty-five pile trestle works were needed to carry the
Central across Sawyer and Douglas Counties into Superior.
This portion of the Duluth extension was not opened for traffic until
January 14, 1909. For about a year traffic on the Owen-Superior
section was confined to freight movements only, and as the roadbed became
firmly fixed and improved, passenger trains entered the extension on regular
schedules in 1910. The new line made the Central the shortest route between
Superior and Chicago.
Probably the toughest part of the Central's job in building the Duluth extension
arose within the city of Duluth where the right-of-way lies along
Superior Street in the solid rock. The contractors, Lantry Construction
Company, of Kansas City, undertook the work of blasting through 1800 feet
of hard rock to reach the new passenger station.
The terminals of the Central at Superior and Duluth are wholly owned.
From Superior to Duluth the Central mileage is 7, and in covering this
route the facilities of the Soo Line, the Interstate Bridge, and the Duluth Terminal
Railway are used in part by freight traffic. Except the Interstate
Bridge and approaches, the passenger trains of the Central operated on
their own rails between Superior and Duluth.
In 1909-1910, as a final move to provide a straight shot line to Duluth
and a shorter easier route to St. Paul, the Central built the Spencer-Owen
cut off involving about 19 miles of construction.
The new cut-off shortened the overall distance From Chicago to St. Paul
and Duluth by about 9 miles; moreover, eliminated the Abbotsford triangle,
always a "sore thumb" in the affairs of the Operations Department. In 1910
when the Spencer-Owen cut off opened the new gate to the north, Owen inherited
the division headquarters previously located at Abbotsford.
President Whitcomb did not stay to witness the fruit on of his well
designed scheme for the Duluth Line, and retired from office in 1906. Earlier
in 1906, the Cincinnati, Hamilton & Dayton Railroad entered the sphere
of influence in the affairs of the Central, and Wm. A. Bradford, a former
director of the C.H.&D. took the office vacated by H. F. Whitcomb. |