The Bancroft depot was erected
on the old Portage Line which ran from Stevens Point to Portage, Wisconsin.
The line was known as the P-line and served the towns of Plover, Bancroft,
Plainfield, Hancock, Coloma, Montello, Packwaukee and Endeavor. Dating
from the very early 1870’s, it was originally developed by the Portage,
Winnebago & Superior railroad. On February, 1871 it became the Wisconsin
Central, Inc.
No exact date exists for
when the depot was built but estimates point to 1897. The last train to
use this line arrived in Stevens Point, November 8, 1945. The following
year dismantling began.
The Wisconsin Central was operated by the Soo Line beginning
April 1909, but retained its own corporate identity until January 1, 1961
when it merged into the Soo Line railroad company.
It seems like years ago (1987)
when murmurings about a depot being available for restoration and to be
moved to become part of the Portage County Historical village in Plover.
Upon seeing the old dilapidated building, I thought this was going to take
a miracle and with the expense to get it
moved
- a miracle plus.
Well things seemed to come
together fast, with Wisconsin Public Service agreeing to move the power
lines, the Soo Line Historical
& Technical Society donating money, and the Portage County Historical
Society allotting money for the move. The Central Wisconsin Model Railroaders
were then asked to attend a Portage County Historical Society meeting.
The purpose of the meeting was to inquire if the CWMR would become a source
of help in this venture. The agreement that evolved was that as a result
of a $1000 donation for the basement and foundation, the CWMR would be
allowed to construct a clubhouse in the basement of this historic structure.
In the summer of 1989, everything
came together and Pukal Trucking of Wittenberg got the contract to move
the structure.
1990 - Year 2
When spotted being moved on
June 13, 1990, the cry came loud and clear to the CWMR! The depot had arrived;
it was finally here and our apprehensive enthusiasm was triggered.
After the structure was
set on its foundation the work on the exterior began. First, all
of the damaged and destroyed material was removed. Doors and windows that
were added to the structure throughout the years were also removed, returning
the structure to it original design.
Let me tell you, there was
work to be done virtually everywhere. The first order of business was to
shore up all main structural damage, supporting outside walls, corners,
sills, etc. This prepared
us
for replacing the siding where needed. Feltz Lumber special cut the siding
planking to the original sizes. There was a big problem with regard to
the batting strips needed to cover the planking. Where do you get batting
designed in the late 1800's. An old friend, Jerome Kobishop, came
to mind; he surely would know where to get this. As things turned out,
he not only knew but also volunteered to make it - 500 ft of batting, exactly
as the original. At this point we knew this project was to be a real challenge!
With the onset of winter,
the depot had only received its new repaired siding and work ceased until
the spring of 1991.
1991 - Year 3
Work began immediately as
the weather became conducive to working outdoors. This year would see the
scraping of old paint and applying the primer. The open doors and
windows were
sealed
off - lots of broken glass. Chuck Oswald was hired to repair the damaged
roof structure and he proved to be a very capable repairman - do you know
how high it is up there? New rafters, roof boards and fascia were installed
where needed. Tarpaper was put over suspected leaks. A major leak problem
over the agent area was identified and repaired.
The building was beginning
to gain a foothold against the elements, which had had their way for several
decades. We now felt if only we could get a roof on this thing, we would
be out of the woods. It was not to happen in 1991. The fall was approaching
fast and winter was once again upon us.
1992 - Year 4
The year 1992 would become
a very demanding year for the CWMR. Things began to happen at a rapid pace.
Because we had only primed the exterior, it was imperative that the building
receive a finish coat of paint. Enter a new dilemma - what color.
Some felt from pictures it should remain gray with white trim - others
thought it was originally a brown with yellow trim. Unable to determine
the exact shade of brown used originally, it was decided to go with the
yellow with maroon trim of Soo heritage.
Carl Whittaker, a CWMR member,
began communicating with the Soo Line Historical Society. Larry Easton
had depot paint chips. These were analyzed and computer matched. With the
approval on the colors from the SLHS, paint was purchased and finish coats
were being applied when we ran into another delay. The PCHS halted the
painting procedure until they were sure the color was correct. Two
weeks passed and a PCHS committee meeting was called to resolve this issue.
Carl presented all the facts to the PCHS, who agreed we should go ahead
with the color scheme of yellow and maroon.
During the period of waiting
for the final okay on the paint issue, work continued on the freight doors
and sills. During one of our work sessions the Waupaca Model Railroaders
volunteered their time and came to help. We sure appreciated their help,
as we completed rebuilding one of the large freight doors that evening.
Work was also completed on repairing all damaged sub-flooring inside the
agent’s office of the depot.
On arriving at the depot
one night for a work session there came another surprise; someone had left
approximately 30 square of asphalt shingles in the freight room. We didn’t
know where they came from until a week later - the Wisconsin Central Limited
Railroad had donated them for use on the depot. This in turn brought up
another controversy, as the depot was to be refurbished to a time
period
around the turn of the century and this decided upon cedar shingles. "Old
Yeller" as it now became to be known, would have to wait again for its
much needed protective headgear. The Wisconsin Central said it was all
right to use the shingles on another roof.
It was now up to the PCHS
to make its decision as we were approaching mid-summer and another year
without some sort of roof would start reversing all the fine work already
done to preserve the structure. It was finally decided that cedar shingles
would be the proper application but the expense proved to be another hurdle.
Excellent planning by the PCHS overcame this hurdle, and Boyles Roofing
of Wisconsin Rapids was contracted to install the roof the second week
in August. Well...it would be the second week in September before
work began, but with great jubilation, as the roofers began taking off
four layers of shingles and other types of roofing, exposing the original
roof boards for the first time in about 100 years.
With the painting in its
final stages and the roofing going on, along with some final trim, it was
a sight to behold for the work crew to see it all come together at once.
1993 - Year 5
It has again become that
cold time of year and "old yeller" has spent its third winter at Heritage
Park. Much still had to be done to bring the depot all the way back to
its original status but the refurbishing was well on its way!
Still planned for the Bancroft
depot would be the reinstallation of the windows, a replica of the
platform
out front, and the interior work for the waiting room, operator’s bay,
and freight room. Several other ideas, and/or dreams were already being
conjured up to give it atmosphere, such as an operating semaphore, a spur
along the front of the depot with the possibility of an old caboose being
spotted there. Other artifacts pertinent to the era could also be placed
in or outside the depot.
It had been a productive
three summers and results had been somewhat spectacular. The Bancroft depot
probably looks as good now as anytime since the early 1920's.
1994 - Year 6
It is now the spring of 1994
and we are to begin the arduous task of restoring the waiting room. All
trim and doors were removed. Walls were repaired where needed, again with
the help of Feltz lumber; we were able to duplicate the wainscot needed
for the walls. While Don Kottke worked on the room trim and doors, Jerome
Kobishop and Fred Haase worked on replacement doors parts. Enter another
fellow who was able to reproduce the damaged window and doorsills.
Dennis Lauer gave of his own time to reproduce exact duplicates of the
sills in his fine workshop.
During this time, many members,
along with Mike Eiden and his "have sander will travel", began the endless
task of power sanding the entire waiting room to get it ready for it first
coat of paint in many, many years. At the same time, many members began
the gruesome task of cleaning the hardwood floorboards. Don Anderson, even
took flooring home to clean...there were tests on him for normalcy.
After a month of sanding
and puttying, Jerry Rohlinger’s paint crew, along with second-story men,
Carl Whittaker, Dean Sauve, Scott Janz, and Mike Rutta, started priming
the room. With the completion of the painting, it was time to think about
getting started on the windows.
With the aid of Anton Anday
and the PCHS providing the $1200 needed to make the sashes for the building,
Carl Whittaker provided the measuring and ordering of the sashes from G
& S Woodworking. Exact duplicates were produced to re-window the entire
depot.
This produced another endless
task of giving each sash five coats of paint before installation. Because
there are six panes in each sash, the painters, Fred Simons and Jerry Rohlinger’s
eyes began to cross. If you don’t believe me, take a look. We now know
why they call these panes (pains).
It was now time to
install the windows (no problem) except these are the type with counter
weights. Ask Fred Haase and Larry Misiewicz how simple it is to get the
sash ropes installed. I’m sure you will get a chuckle out of them.
With the waiting room windows
and trim installed and the room painted, we have almost attained our goal
for the summer.
Larry Misiewicz and his
crew started the hardwood floor project September 10. During the month
of September, work was begun on the heavily damaged portion of the agent's
room, an area where a tree had grown through the entire side of the building
and caused excessive damage and dry rot. New ceiling joists and wall construction
was completed, a new window casing, reproduced by Dennis Lauer, was also
installed. New wainscoting was installed on the south wall and ceiling
where needed.
Next was to replace the
landing to the upstairs stairwell, and the two stairways between the freight
room and agent's room.
The agent's room is close
to being ready for puttying and sanding. Since this work was not scheduled
for 1994, we were ahead of schedule and it allowed us a good chance to
finish the agent's room sometime during the summer of 1995.
1995 - Year 7
The summer of 1995 will be
devoted to the ticket agent's room. In 1994 the room had been site cleared
and all repairs had been competed except for the main structure between
the two large bay windows.
Sanding began with sometimes
4 sanders going at once. The noise was awesome. Jim Miller, Carl Whittaker,
Mike Rutta and Mike Eiden looked like ghosts, shrouded in old paint chips
and dust.
Meanwhile, Don Kottke, was
up to his old tricks of completely redoing all the windows and door trim.
Most of these had been removed. The boards were first power sanded and
then every board was checked for cracks and splits. These were all re-glued
and straightened as well, as could be. It seemed each board had a hundred
holes to re-putty. The boards were then re-sanded and re-puttied and sanded
again. This had to be done for 10 different components for each of the
5 windows in the agent's room alone. After this, they were primed and given
two coats of trim paint.
Meanwhile, Bruce Heath did
a yeoman job of getting all the sashes painted for this room. Bruce spent
a lot of tedious hours getting the 10 sashes done. In all there were 5
different coats of paint.
It all came together late in June when Jerry Rohlinger’s group
got the room primed and gave it the first coat of paint. Shortly after,
Don Kottke and Fred Haase spent a long, long Saturday with Ed Bochenek
installing the windows. For the most part these fit nicely, but there were
big problems on the two small side windows. These were about a quarter
inch too narrow. The window casings had to be adjusted along with some
shims to the sashes to custom fit these windows.
Some work was being done
to complete the floor in the waiting room by Larry Misiewicz and Bob Bochenek
but this was hindered by a lack of correct flooring materials. It was decided
to remove enough flooring from the agent's room to finish the waiting room.
The big problem was that the material was in many different widths.
After the waiting room was
given its second coat of paint, work began in the stairwell, being sanded
and given a first coat.
1996 - Year 8
We began the spring of 1996
with ardent vigor to complete the first or main floor of "ole yeller".
Main targets for this year were to install the final windows, complete
the interior of the dispatch office and complete installation of the hardwood
floor.
With the help of Fred Haase,
Don Kottke completed the window installation. All windows on the main floor
are now operable with locks, pulls, and counter-weights installed. The
windows on the second floor were sized and installed, but are only tacked
in place.
At this time, the arduous
job of laying the remaining hardwood flooring began. After a big
Saturday
work session, the task of sanding this 100-year old hardwood was ready
to begin. What a job for Larry Misiewicz and his power sanding machine.
Larry spent many, many hours traversing this old wood and changing many
belts as the old floor had many undetected square nails and sharp uneven
corners. But Larry prevailed and so with some hand sanding got the floor
ready for sealer. I think Larry may have celebrated a little after this
chore. Am I right Larry?
Now Jerry Rohlinger began
the final sealing of the floor and final wall painting. At this time we
ran into another problem. The new paint obtained from Fleet Farm did not
match the coded paint purchased previously. After several hours with the
paint mixer at Fleet, we were able to get the new paint close enough to
match the original color and the final touch-up was completed.
Enter my wife, Judie Kottke.
When she saw the rooms, she mentioned that shades were shown in the depot
picture we have in the clubhouse. So to improve the looks of the depot,
she proceeded to obtain these shades. She and Don installed said shades
and "walla"...the rooms now look impressive.
By July 4th the depot was
ready for it first open house scheduled for July 16th. Some work still
remains, but we finally have it under control. With the help of the Bochenek's,
Ed and Bob, the remaining gaps in the freight room walls were patched up.
This has this room looking respectable as well.
At the time of this writing,
work was begun on the platform on the ends and south side of the depot.
The Lutheran Brotherhood donated a substantial amount of cash to the PCHS
for this project, which allowed the work to begin.
1997 - Year 9

It was a fairly quiet year for
the depot. The year began with "ole yeller" getting a brand new
coat
of paint. Fred Haase and Don Kottke completed the task in nine days. Fred
spent a lot of time during the week on the high ladder. Don and Fred also
installed the new ticket window and a new agent's desk.
Jerry Rohlinger sanded and
painted the window and desk. This completed the agent room as far as refurbishing
is concerned. Clean-up of the freight room began in July for the national
NMRA meet. Tours from Madison would stop here for a dinner served by our
club.
Main entry door locks were
purchased and will be installed next spring. The Lutheran Brotherhood has
donated planking for the rear platform, one half has been installed. In
October the security system for the depot was activated.
1998 - Year 10
The platform was installed
on the south side of the depot. Plans for completing the rest of the platform
are being made for 1999. Significant donations from the Lutheran Brotherhood
Central Wisconsin Branch # 8101, of approximately $5,500 in the last two
years, has made this possible. An additional $2-3,000 is required to complete
this aspect of the restoration. The only other major project for completion
of the depot is the installation of the chimney.
July 18 & 19th, the
Portage County Historical Society’s first Plover Portage Rendezvous, featuring
re-enactors of the Fur Trade Era drew approximately 1,700 visitors to the
Park. The depot being of a unique architecture was a high point for many
of the guests.
Artifacts are being restored
or obtained for the interior. This portion of the restoration will continue
for many years as items are donated etc. Some rail and ties have been obtained
for the siding. Trucks were donated by the Wisconsin central Limited
for a Green Bay & Western outside braced wood boxcar that has been
given to the Society. Work on this will begin in 1999. The last, and possibly
the most important project, is the restoration of the original "two holer
privy". This will commence soon?
This is how the depot looked
on Sept. 12, 1998. Photo provided by members of Central Wisconsin Model
Railroaders, Ltd.